Delivering Modular Cargo to Remote Construction Project for an International Oil Consortium

Working in a remote, extreme environment in the Russian Far East, Foss helped a major international oil consortium transport 36 prefabricated modules to support construction of an LNG production facility at the northeast tip of Sakhalin Island.  Transporting the 280' long x 45' wide x 85' tall modules—which weighed up to 1,800 tons––required complex logistics as well as combating environmental challenges from ice, typhoons and dangerous sea conditions.

From 2005-2006, a team of Foss operations managers, engineers, equipment operators and marine personnel successfully managed the marine transportation, logistics, supply chain management, dredging and heavy haul delivery of two of the largest sealifts in decades, using Foss U.S. flag and foreign flag ocean going tugs and heavy lift barges to transport the modules from Ulsan, South Korea to Sakhalin Island. Three Foss U.S. flag harbor tugs served as shallow water assist tugs to safely navigate the barges over the bar through the narrow channel entrance for set down and discharge in the shallow water basin. The Foss team ballasted the barges onto the bottom and, working in tandem with Mammoet Heavy Haul, completed the final transfer ashore. The project was completed ahead of schedule, on budget, safely and with all materials delivered in good condition.

Read a profile of Foss’ work in the March, 2007 Oil and Gas Journal, and April, 2007 Offshore Oil and Gas Financial Journal.

Foss stresses safety, quality, and environmental compliance in all our projects, at home or internationally.

A Foss tug maneuvers a barge with project cargo to the deck at Chayvo, Sakhalin Island, Russia.

Foss works with local contractors to provide end-to-end project management for complex cargo moves.

Foss works with Mammoet Heavy Haul to move a very large module inland from the barge terminal on Sakhalin Island.

Foss and our heavy lift contractor coordinate a complicated project cargo move.